A Mastladder safety rail ladder securing high pylones
Printable verison with more photosFallprotec fitted out Mastladders to the four 50 m high pylons at the Georges Suant football stadium, in the outskirts of Paris. The site consisted of replacing a used suspended basket with our Mastladder. This operation required an on-site measurement to ensure that no interference penalized the installation, especially at the level of the upper floor. Drilling or welding could not be used to fix the ladder to the pylon. As a means of attachment, strapping was preferred. In fact, this process does not alter the corrosion resistance of the pylone.
Fallprotec was also present during the installation and commissioning of the ladders. The client expressed great satisfaction. In fact, at all stages of the project, he was able to rely on the expertise of Fallprotec, which led the project from start to finish.